Indiana Utility Regulatory Commission (Indiana Michigan Power) — I&M Industrial Power (Large Load) Tariff Settlement Order (Cause No. 46097)
Indiana Utility Regulatory Commission (Indiana Michigan Power) · I&M Industrial Power (Large Load) Tariff Settlement Order (Cause No. 46097)
The Indiana URC approved a settlement modifying Indiana Michigan Power's Industrial Power Tariff for facilities of at least 70 MW (or 150 MW aggregated), requiring 12-year contracts, minimum monthly demand charges of 80% of contract capacity, exit fees, and collateral so grid-upgrade costs fall on data centers rather than existing ratepayers.
Technical detail
The Indiana URC approved a settlement modifying Indiana Michigan Power's Industrial Power Tariff for facilities of at least 70 MW (or 150 MW aggregated), requiring 12-year contracts, minimum monthly demand charges of 80% of contract capacity, exit fees, and collateral so grid-upgrade costs fall on data centers rather than existing ratepayers.
Who is protected: People subject to this body's AI/surveillance systems.
Who must comply: Indiana Utility Regulatory Commission (Indiana Michigan Power)
Key facts
| Jurisdiction | Indiana Utility Regulatory Commission (Indiana Michigan Power) |
|---|---|
| Level | State |
| Status | In effect |
| Protection strength | Limited protection |
| Effective date | 2025-02-19 |
| Citation | I&M Industrial Power (Large Load) Tariff Settlement Order (Cause No. 46097) |
| Topics | data-center siting and energy · consumer protection · government use of AI |
| Last verified | 2026-07-01 |
| Official source | Indiana regulators approve 'large load' interconnection rules | Utility Dive ↗ |
Related data-center siting and energy rules elsewhere
- Emergency 365-day moratorium on new data centers (>20 MVA) · In effect
- Resolution setting Seattle data-center impact-study framework · In effect
- Six-month moratorium on data centers >350,000 sq ft (Minneapolis) · In effect
- Nashville/Davidson County temporary moratorium on data centers · Proposed / pending
- Two-year moratorium on data centers, crypto mining, battery storage · In effect
- One-year data-center moratorium in unincorporated Boone County · In effect
See something wrong or out of date? Submit a correction — every entry must carry a verifiable official source.