HomeLegal DirectoryAEP Ohio Data Center Tariff Order (Case 24-0508-EL-ATA)

In effect Limited protection

Public Utilities Commission of Ohio (AEP Ohio) — AEP Ohio Data Center Tariff Order (Case 24-0508-EL-ATA)

Public Utilities Commission of Ohio (AEP Ohio) · AEP Ohio Data Center Tariff Order (Case 24-0508-EL-ATA)

The Ohio PUC adopted a settlement creating a new data center customer class for loads of 25 MW or greater, requiring those customers to pay for at least 85% of contracted capacity for a minimum 12-year term plus exit fees and financial assurances to prevent cost-shifting to other customers.

Technical detail

The Ohio PUC adopted a settlement creating a new data center customer class for loads of 25 MW or greater, requiring those customers to pay for at least 85% of contracted capacity for a minimum 12-year term plus exit fees and financial assurances to prevent cost-shifting to other customers.

Who is protected: People subject to this body's AI/surveillance systems.

Who must comply: Public Utilities Commission of Ohio (AEP Ohio)

Key facts

JurisdictionPublic Utilities Commission of Ohio (AEP Ohio)
LevelState
StatusIn effect
Protection strengthLimited protection
Effective date2025-07-09
CitationAEP Ohio Data Center Tariff Order (Case 24-0508-EL-ATA)
Topicsdata-center siting and energy · consumer protection · government use of AI
Last verified2026-07-01
Official sourcePUCO orders AEP Ohio to create data center specific tariff | Public Utilities Commission of Ohio ↗

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction — every entry must carry a verifiable official source.