Oregon Public Utility Commission (Portland General Electric) — Order 26-154 Approving PGE Large-Load Tariff Framework for Data Centers
Oregon Public Utility Commission (Portland General Electric) · Order 26-154 Approving PGE Large-Load Tariff Framework for Data Centers
The Oregon PUC approved a large-load tariff for data centers exceeding 20 MW that requires customers to fund 100% of distribution upgrades, sign 10-to-30-year contracts, pay minimum demand charges at 90% of contracted capacity, and adds a 1 cent/kWh surcharge on projects over 100 MW to offset residential and low-income customer costs. In July 2026 the PUC approved PGE's compliance rate filing implementing the framework: data-center customers' rates rise about 29.7% while residential bills drop about 1.3%.
Technical detail
The Oregon PUC approved a large-load tariff for data centers exceeding 20 MW that requires customers to fund 100% of distribution upgrades, sign 10-to-30-year contracts, pay minimum demand charges at 90% of contracted capacity, and adds a 1 cent/kWh surcharge on projects over 100 MW to offset residential and low-income customer costs. FOLLOW-ON (July 7, 2026): the PUC unanimously approved PGE's compliance rate filing implementing the large-load/data-center framework under HB 3546 (POWER Act) — average 29.7% rate increase for data-center customers effective July 8, 2026; residential bills decrease ~1.3%, commercial ~2.1%, other industrial ~1.4%.
Who is protected: People subject to this body's AI/surveillance systems.
Who must comply: Oregon Public Utility Commission (Portland General Electric)
Key facts
| Jurisdiction | Oregon Public Utility Commission (Portland General Electric) |
|---|---|
| Level | State |
| Status | In effect |
| Protection strength | Limited protection |
| Effective date | 2026-05-07 |
| Citation | Order 26-154 Approving PGE Large-Load Tariff Framework for Data Centers |
| Topics | data-center siting and energy · consumer protection · government use of AI |
| Last verified | 2026-07-19 |
| Official source | Oregon PUC approves PGE's large-load tariff framework for data centers | Utility Dive ↗ |
Related data-center siting and energy rules elsewhere
- Emergency 365-day moratorium on new data centers (>20 MVA) · In effect
- Resolution setting Seattle data-center impact-study framework · In effect
- Six-month moratorium on data centers >350,000 sq ft (Minneapolis) · In effect
- Nashville/Davidson County temporary moratorium on data centers · Proposed / pending
- Two-year moratorium on data centers, crypto mining, battery storage · In effect
- One-year data-center moratorium in unincorporated Boone County · In effect
See something wrong or out of date? Submit a correction — every entry must carry a verifiable official source.