Palm Beach County, FL Denial of Project Tango 600MW AI Data Center Campus

Palm Beach County, FL · Palm Beach County, FL Board of County Commissioners 5-1 denial without prejudice, July 16, 2026, Project Tango 600MW data center campus

Palm Beach County, Florida commissioners rejected 'Project Tango,' a proposed 600-megawatt AI data center campus in the Loxahatchee area, by a 5-1 vote on July 16, 2026 after a marathon hearing lasting about 12 hours. The denial was 'without prejudice,' meaning the developer can come back with a revised application. The county's zoning commission had already recommended against the project on July 2. Note: a previously approved 202-acre Central Park Commerce Center project still allows some data center space in the county.

Technical detail

Palm Beach County (FL) Board of County Commissioners 5-1 vote, July 16, 2026, denying WITHOUT PREJUDICE the applications for Project Tango, a 600MW AI data center campus proposed near Loxahatchee. Hearing ran approximately 12 hours. Zoning Commission recommendation against the project issued July 2, 2026. Denial without prejudice permits refiling. Caveat: the earlier-approved 202-acre Central Park Commerce Center retains entitlements allowing some data center space — this denial does not eliminate all DC development capacity in the county.

Who is protected: Palm Beach County, FL residents, particularly the Loxahatchee area

Who must comply: Project Tango applicant/developer; future large data center applicants in Palm Beach County, FL

Key facts

JurisdictionPalm Beach County, FL
LevelCounty
StatusIn effect
Protection strengthModerate protection
Effective date2026-07-16
Enacted2026-07-16
CitationPalm Beach County, FL Board of County Commissioners 5-1 denial without prejudice, July 16, 2026, Project Tango 600MW data center campus
Enforced byPalm Beach County, FL Planning, Zoning and Building; Board of County Commissioners
PenaltiesApplication denial (without prejudice — refiling possible)
Topicsdata-center siting and energy
Last verified2026-07-19
Official sourceProject Tango AI data center rejected in Palm Beach — WLRN ↗

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction — every entry must carry a verifiable official source.