Pasco County, FL 1-Year Moratorium on Large Data Centers (>2.5MW)

Pasco County, FL · Pasco County, FL Board of County Commissioners action, July 14, 2026, 1-year moratorium on data centers >2.5MW

Pasco County, Florida (north of Tampa) adopted a one-year moratorium on July 14, 2026 covering large data centers — those that would use more than 2.5 megawatts of power. The county will use the year to develop regulations for data center siting.

Technical detail

Pasco County (FL) Board of County Commissioners action July 14, 2026: 12-month moratorium on data centers exceeding a 2.5MW power threshold (through approximately July 14, 2027). Notably low MW threshold compared to peer Florida counties (Sarasota's is 50MW), giving the pause broad practical scope.

Who is protected: Pasco County, FL residents

Who must comply: Developers of data centers >2.5MW seeking approvals in Pasco County, FL

Key facts

JurisdictionPasco County, FL
LevelCounty
StatusIn effect
Protection strengthModerate protection
Effective date2026-07-14
Enacted2026-07-14
CitationPasco County, FL Board of County Commissioners action, July 14, 2026, 1-year moratorium on data centers >2.5MW
Enforced byPasco County, FL Planning and Development; Board of County Commissioners
PenaltiesPermit/application denial during moratorium
Topicsdata-center siting and energy
Last verified2026-07-19
Official sourcePasco County adopts one-year moratorium on large data centers — WUSF ↗

Related data-center siting and energy rules elsewhere

See something wrong or out of date? Submit a correction — every entry must carry a verifiable official source.